Construction progress of 10 MW storage project in Bordesholm

16. Okt 2018

RES group and the regional utility VBB build 10-MW-Li-ion-storage-unit in Schleswig-Holstein

Three months after start of construction, the topping-out ceremony for the 10 MW battery storage facility in Bordesholm was celebrated. As RES (Renewable Energy Systems Ltd) stated in a press release, the good collaboration between RES group and the regional utility VBB made a significant contribution to the smooth construction progress in reaching this important project milestone. The battery storage system will provide grid stabilisation and back-up power fed from 100% renewable energy to the community when there is grid disruption or upstream grid failure.

The project is funded by Schleswig-Holstein’s ministry for economy from EU funds.

Find more information at www.vb-bordesholm.de und www.res-group.com.

Cookie-Einstellungen

Diese Webseite nutzt Cookies und externe Komponenten, welche dazu genutzt werden können, Daten über Ihr Verhalten zu sammeln. Sie entscheiden, welche Cookies und externen Komponenten Sie zulassen oder ablehnen. Technisch notwendige Cookies werden auch bei der Auswahl von ablehnen gesetzt. Ihre Entscheidung können Sie jederzeit ändern. Weitere Informationen auch in unseren Datenschutzinformationen